Primavera Contract Management Standard Procedure

 

Informal Bids (Projects Under $35K)

 

Menu

 

 

PREPARATION OF PLANS/SPECS

 

If your project estimate is under $35,000.00, the project can be managed as an informal project.  The Project Manager (or Engineer) will:

 

1.

Provide evidence of environmental clearance on project

 

 

2.

Assure that right-of-way easements or permits have been obtained, if applicable

 

 

3.

Initiate Project Approval Request

 

 

4.

Initiate Project Approval Request form (EN-182)

 

 

5.

Prepare specifications (example format can be found under:
j:\wordproc\word\engineer.31\nieblas\$spec\informal.spc

 

 

6.

Make necessary arrangements for soils, surveying, and cathodic protection services if needed on project

 

The Construction Project Administration Supervisor (CPAS) will:

 

a.

Type specifications

 

 

b.

Forward specifications for review

 

 

c.

Forward original spec to Clerical for reproduction

 

 

d.

Make arrangements to have plans reproduced (if project contains very few plans, the District will be used for reproduction services)

 

 

e.

Prepare meeting notification

 

 

f.

Provide you with bidding sheets for you proposal package

 

Go to Top

 

 

ENGINEER’S ESTIMATE

 

Run a copy of bid sheets for the Project Engineer to fill in for the Engineers estimate (include unit prices for each bid item).  File Engineer's Estimate.

 

Go to Top

 

 

PLANHOLDERS LIST

 

A preferred list of contractors will be prepared by the Director of Field Engineering.  Contact the DFE for the preferred list and prepare the mailing labels (check with the Project Engineer if you need to mail them overnight).  File the planholders list in the project file for future reference.

 

When specification and plans are finalized, the CPAS will provide you with the Proposal Package.  Make the necessary copies to insert into the preferred contractor’s specification.  Mail the plans/specs to the preferred contractor’s list.

 

Distribute the Bidding Information Sheet as follows:

 

 

Original

-

working file or spec. book

 

 

 

 

 

1

-

Const. Project Admin. Supervisor

 

 

 

 

 

1

-

Sr. Const. Admin. Rep.

 

 

 

 

 

1

-

Project Manager

 

 

 

 

 

1

-

Inspection Manager

 

 

 

 

 

1

-

Receptionist/AC Lobby

 

 

 

 

 

1

-

Receptionist/Contracts

 

 

 

 

 

1

-

Specification book

 

 

 

 

 

1

-

John Ward

 

 

 

 

 

1

-

Community Involvement

 

Distribute the plans/specs in house as follows:

 

 

1

-

Project Engineer (plans and specs).  Ask the Project Engineer if he needs 2 copies of the plans for soils/surveying services

 

 

 

 

 

1

-

Project Manager (plans and specs)

 

 

 

 

 

1

-

Construction Administrator (plans and specs)

 

 

 

 

 

1

-

Supervising Engineering Inspector (plans and specs)

 

 

 

 

 

1

-

Inspector (plans and specs)....identify "INSPECTOR"

 

 

 

 

 

1

-

Specify one only: (1 set of plans and specs):

     * Director of Water (Khos Ghaderi) or

     * Director of Maintenance (Touissant Williamson) or

     * Director of Sewer (John Jannone) and

        Treatment Plant Manager (if project is at an RWRF)

 

Go to Top

 

 

PRE-BID WALK-THROUGH

 

If a pre-bid walk-thru (perhaps “mandatory”) is required, forward a “PRE-BID WALK-THRU AGENDA” form to the Project Engineer for completion (scope of work, etc.).  Take a “SIGN-IN SHEET” and make sure that all attendees (including EMWD representatives) sign-in.  If mandatory, all attendees are required to stay for the entire walk-thru meeting.  Verify, again, that all attendees signed-in.

 

Project Engineer prepares "Pre-Bid Walk-Thru Questions and Answers" to be distributed to all planholders.  Any questions asked requiring modification to specification will be answered thru an Addendum or Letter of Clarification (refer to Addenda procedures).

 

Go to Top

 

 

RECEIPT OF BIDS

 

When it’s time to receive bids, either make arrangements for yourself or the Project Engineer to pick up the bids.  When bids are received (no public bid opening is required), selection shall be made to the lowest, responsive bidder.

 

 

NOTE: Only those contractors who received the Informal Bid Packet are allowed to submit a bid.

 

 

No copies shall be made of any bid proposal until after District review.

 

Go to Top

 

 

BID SUMMARY

 

Distribute Bid Summary sheets as follows:

 

 

CAR’s

 

Sr. Construction Administration Representative

 

Construction Project Administration Supervisor

 

Project Engineer

 

Project Manager

 

Construction Administrator

 

Director of Field Engineering

 

Specification File

 

 

 

Remember... when calls come in requesting information on bid results, state “Apparent Low Bidder is...”

 

 

Go to Top

 

 

BID PROPOSAL REVIEW

 

Copy 3 sets of all bids for complete review and verify that all pages have been copied (Do not mark on originals). Keep one for your review and distribute others with copy of bid summary and state “Please Review and Return ASAP” to:

 

 

Construction Administrator

 

Director of Field Engineering

 

File originals in the spec file.

 

Review the bid price extensions and additions of all bids (initial by any corrections made in red ink, signifying additions/extensions are correct).  Before throwing envelopes away, check to see if there's any information on envelope (phone #, zip code, etc.) that's not on bidding sheet.

 

Forward your reviewed bids to Senior CAR for review.

 

The Construction Administrator and you will review all bids for comparison of irregularities noted.  The Director of Field Engineering will review the bids and return them to you.  Legal Counsel recommendation may be sought.

 

After complete review, CAR can revise the bid summary to identify if any bids are deemed "non responsive", if applicable.

 

Go to Top

 

 

EXPERIENCE MOD. RATING

 

At this time, forward the apparent low bidder’s proposal package to the Construction Project Administration Supervisor with a sticky note stating:  Need EX MOD rating.  The proposal package will be returned to you for further processing.

 

Go to Top

 

 

PREPARING AGREEMENT

 

Once the responsive bidder is selected, the Project Engineer needs to complete the agreement through the Purchasing/Contracts Dept.

 

Project Engineer needs to attach the original bid proposal to the agreement/POR and forward it to the Contracts Department for processing.

 

Keep in close contact with the Contracts Department in order to keep the CA, DFE and PE informed of the status of the agreement routing.

 

Go to Top

 

 

SAFETY PRECONSTRUCTION/PRECONSTRUCTION CONFERENCE

 

Once the agreement is fully executed, the Contracts Department will provide you with a copy of the agreement.

 

Prepare the Notice to Proceed.  Make the arrangements to schedule the safety preconstruction conference and the preconstruction conference (refer to these specific procedures)

 

Identify the pre-job meeting & safety meeting time & date on the Notice to Proceed.  REFER TO PRE-JOB AND SAFETY PRE-JOB procedures.  (Refer to example attached).  The contract start date is considered the same date of the pre-job meeting.

 

When completed, forward to the Asst GM/Engineering for signature.  When returned, fax a copy of the Notice to Proceed to the Contractor as well as the list of forms that needs to be submitted at the pre-job & safety pre-job meeting.  The original is to be handed to him at the pre-job meeting.

 

 

Distribute the Notice to Proceed to:  CA, PE, Inspector, Specification File, and CPAS.

 

 

Go to Top

 

 

FORMS TO BE SUBMITTED BY CONTRACTOR

 

List of Documents to be mailed with the notification meeting to the Contractor and returned by the Contractor at the pre-job are as follows:

 

Current Prevailing Wage Rates (State)

 

 

Certified Payroll Form (EN-146)

 

 

Submittal Procedures

 

 

Trench Shoring (EN-57), if applicable

 

 

RFI (EN-113)

 

 

Change Order Proposal Initiated by Contractor (EN-114a)

 

 

Authorized Signatures

 

 

Verification of Pre-Approved Materials (EN-183)

 

 

Pipe Zone Density Chart (may be a part of submittal)

 

 

Emergency Phone Numbers

 

 

Non Collusion Affidavit requiring Notarial Jurat

 

 

Subcontractors List

 

 

Illness and Injury Prevention Report (if not already on file)

 

 

Project Control Schedule (CPM or Bar Chart)

 

 

Specific Operating Safety Procedures (refer to section 01000)

 

 

NOTE:  Refer to SPECIFICATION procedures for processing the required submittals.

 

 

Go to Top

 

 

PREPARING AND ISSUING SR-6 REJECTION LETTER

 

Type SR-6 (letter to unsuccessful bidders).  The SR-6 letter should be routed with Notice of Acceptance of Proposal as follows:

 

 

Signature:  Asst. General Manager, Engineer FOR General Manager's signature

 

When returned, make 1 copy of each for the Spec File.  Send SR-6 letter to all unsuccessful bids.

 

Go to Top

 

 

MISCELLANEOUS ITEMS

 

Remind the Project Engineer/Manager to complete standard form EN-182, Project Approval Request when the agreement is being processed.

 

 

During construction, the inspector will prepare daily inspection reports to be maintained in the project file.

 

 

CAR will receive all documentation (processing RFI’s and filing inspection reports, etc.)

 

 

If an amendment is needed, it must be processed as an amendment to the agreement, not a change order.  If the amendment amount increases the total contract value to exceed $35,000, board authorization is required.

 

Go to Top

 

 

SUBSTANTIAL COMPLETION

 

Beneficial occupancy will require the inspector to submit an EN-16a, Contract Completion Report indicating substantial completion.  Refer to the Substantial Completion Procedures for further details.

 

Go to Top

 

 

TOTAL COMPLETION AND NOTICE OF ACCEPTANCE

 

Upon achieving total completion, the inspector will submit an EN-16a indicating final completion.

 

CAR will process Notice of Acceptance upon receipt of the final EN-16a.  Refer to the Notice of Acceptance procedures. 

 

Go to Top

 

 

PAYMENT

 

The Contractor will submit an invoice upon project completion, however, payment can not be made until the expiration of the 30-day period following the filing of the Notice of Acceptance.  (In lieu of requiring performance and payment bonds, the Contractor accepts no payment until the 30-day filing period has expired).  This time period allows any suppliers or subcontractors the opportunity to file a stop notice against the Contractor.

 

CAR will verify that certified payrolls have been received and are on file prior to issuing final payment.

 

Process the invoice as specified in the Invoice procedures.

 

 

NOTE: The contractor has the option of submitting performance/payment bonds. In doing so, periodic estimates must be prepared and retention held.

 

 

Go to Top

 

 

PROJECT CLOSURE

 

CAR to close Construction Order (use EN-39a) upon clearance from Construction Administrator and Project Engineer.

 

Refer the Closeout procedures for instructions on closing the CO#.

 