Eastern Municipal Water District
Primavera Contract Management Standard Procedure
Informal Bids (Projects Under $35K)
If your project
estimate is under $35,000.00, the project can be managed as an informal
project. The Project Manager (or
Engineer) will:
1. |
Provide evidence of
environmental clearance on project |
|
|
2. |
Assure that right-of-way
easements or permits have been obtained, if applicable |
|
|
3. |
Initiate Project Approval
Request |
|
|
4. |
Initiate Project Approval
Request form (EN-182) |
|
|
5. |
Prepare specifications (example
format can be found under: |
|
|
6. |
Make necessary arrangements for
soils, surveying, and cathodic protection services if needed on project |
The Construction
Project Administration Supervisor (CPAS) will:
a. |
Type specifications |
|
|
b. |
Forward specifications for
review |
|
|
c. |
Forward original spec to Clerical
for reproduction |
|
|
d. |
Make arrangements to have plans
reproduced (if project contains very few plans, the District will be used for
reproduction services) |
|
|
e. |
Prepare meeting notification |
|
|
f. |
Provide you with bidding sheets
for you proposal package |
Run a copy of bid
sheets for the Project Engineer to fill in for the Engineers estimate (include
unit prices for each bid item). File Engineer's Estimate.
A preferred list
of contractors will be prepared by the Director of Field Engineering. Contact the DFE for the preferred list and
prepare the mailing labels (check with the Project Engineer if you need to mail
them overnight). File the planholders
list in the project file for future reference.
When specification
and plans are finalized, the CPAS will provide you with the Proposal
Package. Make the necessary copies to
insert into the preferred contractor’s specification. Mail the plans/specs to the preferred
contractor’s list.
Distribute the
Bidding Information Sheet as follows:
|
Original |
- |
working file
or spec. book |
|
|
|
|
|
1 |
- |
Const.
Project Admin. Supervisor |
|
|
|
|
|
1 |
- |
Sr. Const.
Admin. Rep. |
|
|
|
|
|
1 |
- |
Project
Manager |
|
|
|
|
|
1 |
- |
Inspection
Manager |
|
|
|
|
|
1 |
- |
Receptionist/AC
Lobby |
|
|
|
|
|
1 |
- |
Receptionist/Contracts |
|
|
|
|
|
1 |
- |
Specification
book |
|
|
|
|
|
1 |
- |
John Ward |
|
|
|
|
|
1 |
- |
Community
Involvement |
Distribute the
plans/specs in house as follows:
|
1 |
- |
Project Engineer (plans and
specs). Ask the Project Engineer if he needs 2 copies of the plans for
soils/surveying services |
|
|
|
|
|
1 |
- |
Project Manager (plans and
specs) |
|
|
|
|
|
1 |
- |
Construction Administrator (plans
and specs) |
|
|
|
|
|
1 |
- |
Supervising Engineering
Inspector (plans and specs) |
|
|
|
|
|
1 |
- |
Inspector (plans and
specs)....identify "INSPECTOR" |
|
|
|
|
|
1 |
- |
Specify one only: (1 set of plans and specs): *
Director of Water (Khos Ghaderi) or
* Director of Maintenance (Touissant Williamson) or
* Director of Sewer (John Jannone) and
Treatment
Plant Manager (if project is at an RWRF) |
If a pre-bid
walk-thru (perhaps “mandatory”) is required, forward a “PRE-BID WALK-THRU
AGENDA” form to the Project Engineer for completion (scope of work,
etc.). Take a “SIGN-IN SHEET” and make sure that all attendees (including
EMWD representatives) sign-in. If mandatory, all attendees are
required to stay for the entire walk-thru meeting. Verify, again,
that all attendees signed-in.
Project Engineer
prepares "Pre-Bid Walk-Thru Questions and Answers" to be distributed
to all planholders. Any questions asked requiring modification to
specification will be answered thru an Addendum or Letter of Clarification
(refer to Addenda procedures).
When it’s time to
receive bids, either make arrangements for yourself or the Project Engineer to
pick up the bids. When bids are received (no public bid opening is
required), selection shall be made to the lowest, responsive bidder.
|
NOTE: Only those contractors
who received the Informal Bid Packet are allowed to submit a bid. |
|
No copies shall be
made of any bid proposal until after District review.
Distribute Bid
Summary sheets as follows:
|
CAR’s |
|
Sr. Construction
Administration Representative |
|
Construction Project
Administration Supervisor |
|
Project Engineer |
|
Project Manager |
|
Construction Administrator |
|
Director of Field Engineering |
|
Specification File |
|
Remember... when calls come in requesting
information on bid results, state “Apparent Low Bidder is...” |
|
Copy 3 sets of all
bids for complete review and verify that all pages have been copied (Do not
mark on originals). Keep one for your review and distribute others with copy of
bid summary and state “Please Review and Return ASAP” to:
|
Construction Administrator |
|
Director of Field Engineering |
File originals in
the spec file.
Review the bid
price extensions and additions of all bids (initial by any corrections made in red
ink, signifying additions/extensions are correct). Before throwing
envelopes away, check to see if there's any information on envelope (phone #,
zip code, etc.) that's not on bidding sheet.
Forward your
reviewed bids to Senior CAR for review.
The Construction
Administrator and you will review all bids for comparison of irregularities
noted. The Director of Field Engineering will review the bids and return
them to you. Legal Counsel recommendation may be sought.
After complete
review, CAR can revise the bid summary to identify if any bids are deemed
"non responsive", if applicable.
At this time,
forward the apparent low bidder’s proposal package to the Construction Project
Administration Supervisor with a sticky note stating: Need EX MOD
rating. The proposal package will be returned to you for further
processing.
Once the responsive
bidder is selected, the Project Engineer needs to complete the agreement
through the Purchasing/Contracts Dept.
Project Engineer
needs to attach the original bid proposal to the agreement/POR and forward it
to the Contracts Department for processing.
Keep in close
contact with the Contracts Department in order to keep the CA, DFE and PE
informed of the status of the agreement routing.
Once the agreement
is fully executed, the Contracts Department will provide you with a copy of the
agreement.
Prepare the Notice
to Proceed. Make the arrangements to schedule the safety preconstruction
conference and the preconstruction conference (refer to these specific
procedures)
Identify the
pre-job meeting & safety meeting time & date on the Notice to
Proceed. REFER TO PRE-JOB AND SAFETY PRE-JOB procedures.
(Refer to example attached). The contract start date is considered the
same date of the pre-job meeting.
When completed,
forward to the Asst GM/Engineering for signature. When returned, fax a
copy of the Notice to Proceed to the Contractor as well as the list of forms
that needs to be submitted at the pre-job & safety pre-job meeting.
The original is to be handed to him at the pre-job meeting.
|
Distribute the Notice to
Proceed to: CA, PE, Inspector, Specification File, and CPAS. |
|
List of Documents
to be mailed with the notification meeting to the Contractor and returned by
the Contractor at the pre-job are as follows:
● |
Current Prevailing Wage Rates
(State) |
|
|
● |
Certified Payroll Form (EN-146) |
|
|
● |
Submittal Procedures |
|
|
● |
Trench Shoring (EN-57), if
applicable |
|
|
● |
RFI (EN-113) |
|
|
● |
Change Order Proposal Initiated
by Contractor (EN-114a) |
|
|
● |
Authorized Signatures |
|
|
● |
Verification of Pre-Approved
Materials (EN-183) |
|
|
● |
Pipe Zone Density Chart (may be
a part of submittal) |
|
|
● |
Emergency Phone Numbers |
|
|
● |
Non Collusion Affidavit
requiring Notarial Jurat |
|
|
● |
Subcontractors List |
|
|
● |
Illness and Injury Prevention
Report (if not already on file) |
|
|
● |
Project Control Schedule (CPM or
Bar Chart) |
|
|
● |
Specific Operating Safety
Procedures (refer to section 01000) |
|
NOTE: Refer to
SPECIFICATION procedures for processing the required submittals. |
|
Type SR-6
(letter to unsuccessful bidders). The SR-6 letter should be routed with
Notice of Acceptance of Proposal as follows:
|
Signature: Asst.
General Manager, Engineer FOR General Manager's signature |
When returned,
make 1 copy of each for the Spec File.
Send SR-6 letter to all unsuccessful bids.
● |
Remind the Project
Engineer/Manager to complete standard form EN-182, Project Approval Request
when the agreement is being processed. |
|
|
● |
During construction, the
inspector will prepare daily inspection reports to be maintained in the
project file. |
|
|
● |
CAR will receive all
documentation (processing RFI’s and filing inspection reports, etc.) |
|
|
● |
If an amendment is needed, it
must be processed as an amendment to the agreement, not a change order.
If the amendment amount increases the total contract value to exceed $35,000, board
authorization is required. |
Beneficial
occupancy will require the inspector to submit an EN-16a, Contract Completion
Report indicating substantial completion. Refer to the Substantial
Completion Procedures for further details.
Upon achieving
total completion, the inspector will submit an EN-16a indicating final
completion.
CAR will process
Notice of Acceptance upon receipt of the final EN-16a. Refer to the Notice
of Acceptance procedures.
The Contractor
will submit an invoice upon project completion, however, payment can not be
made until the expiration of the 30-day period following the filing of the
Notice of Acceptance. (In lieu of requiring performance and payment
bonds, the Contractor accepts no payment until the 30-day filing period has
expired). This time period allows any suppliers or subcontractors the
opportunity to file a stop notice against the Contractor.
CAR will verify
that certified payrolls have been received and are on file prior to issuing
final payment.
Process the
invoice as specified in the Invoice procedures.
|
NOTE: The contractor has the
option of submitting performance/payment bonds. In doing so, periodic
estimates must be prepared and retention held. |
|
CAR to close
Construction Order (use EN-39a) upon clearance from Construction Administrator
and Project Engineer.
Refer the Closeout
procedures for instructions on closing the CO#.
Request the
Project Engineer and Construction Administrator to submit working file to
you. CAR will prepare project file for microfilming and forward to
Records Management.